Autumn Views Subdivision Romsey

Autumn Views: Stage 1- 30 Lot Subdivision Melbourne-Lancefield Rd Romsey

Autumn Views is a 30 Lot Subdivision constructed in 2017-2018.

Developers: Autumn Views Pty Ltd

Designer: North East Survey and Design

Value: $6.5 million

Stage 1 includes the construction of:-

  • Drainage with 300 -900 RCP pipe to a 8 ML Retention Basin, with an outfall drain to the council network
  • Sewer up to 6m deep servicing all blocks. Including concrete pouring of Manholes and Property Connections
  • 15,000 T of Rock extracted installing site infrastructure, through Blasting and Hydraulic Rock Hammers
  • Rock processed onsite and re-used in the roads and footpath
  • Earthworks levelling the site to design level, including the preservation of Topsoil for the blocks at completion.
  • A Water Main servicing all blocks
  • Construction of a Temporary Sewer Pump Station and Rising Main
  • Installation of a Left and Right-hand Turning Lane into the Subdivision off the Melbourne Lancefield Rd
  • Trenching and Co-ordination of Gas and Power subcontractors
  • Installation of Roads and Pavements
  • Concrete works including Footpath, Kerb, Channel and Driveways
  • Liaising with Stakeholders including Developers, Macedon Ranges Shire Council, Western Water, North East Survey and Design and the Office of the Federal Safety Commissioner.

Works complete on-time and in-budget by the Completion date of April 2018. The success in the delivery of Stage 1 will lead to Stage 2 commencing earlier than programmed.