GVW Bulk Water Storage Flow Meters
Description: Replacement of Goulburn Valley Water bulk water storage flowmeters, Avenel and Euroa
Replacement of flowmeters at Avenel & Euroa’s water storage facilities
Site: Avenel & Euroa Victoria
Commenced: April 2019
Completion: May 2019
Girdwood Contracting was contracted to replace the water storage flow meters at Avenel & Euroa which included the following works:-
Challenges in Production:
Both sites required the affected towns water supply to be shutdown and alternate water delivery methods to be arranged by GVW, therefore the window of time allowable to complete the shutdowns and install the pipework was very tight and delays couldn’t occur, this required through planning of the works.