Huntly / Epsom Sewer Rising Mains and Sewer Pumping Stations
Client: Coliban Water
Location: Huntly/Epsom
Contract Type: Construction
Value: 5.8 Million
As the principle contractor for Coliban Water, Girdwood Contracting PTY LTD completed the Huntly / Epsom sewer upgrade over the course of six months, on time and within budget. The project included the construction of two 8.5m deep pump stations, a 200,000L storage tank, 11.5km of rising main and 110m of gravity sewer. As a result of the new infrastructure Girdwood Contracting were able to decommission four existing pump stations.
The Sawmill Rd, Huntly Pump station and storage tank;
- 8.5m deep pump station excavated using box shields
- Two Flygt submersible pumps with a total capacity of 40L/s
- 20mx6m benched 7m deep excavation to install the storage tank
The Epsom Recreational Reserve pump station and gravity sewer;
- 8.5m deep pump station installed through the use of sheet piling
- Two Flygt submersible pumps with a total capacity of 70L/s
- 44m laser guided gravity sewer bore beneath the Midland Hwy at a depth of 6.5m
- 58m of trenched gravity sewer at a depth of 6m
- The construction of four maintenance holes ranging from 6.5m to 4.5m deep
5.5km of single rising main and 3km of dual rising main all in PN16 280mm polyethylene rising main
- Directional drilling
- Bucket wheel trenchers
- A fleet of excavators and smaller machinery
- Varied conditions including sand, clay and rock
- Engagement with local residents and contractors
Pump station decommissioning
- Allen St pump station, 2m removed and the remainder backfilled.
- Ironstone Rd pump station, converted into a maintenance hole
- Sullivan St pump station, converted into two adjacent maintenance holes
- Sawmill Rd Interim pump station, converted into a maintenance hole